The totals are the county checkbook, grouped by department and account. Payment lines are the individual rows behind that total: date, fund, account, description, and invoice. A Board agenda item is listed when its title names this party. The agenda is the board’s record. The checkbook is the payment record. They are not the same document.
By department
| Department | Account | Paid | Payments |
|---|---|---|---|
| Facilities Management | Capital Assets | $242,667 | 22 |
| Facilities Management | Services and Support | $19,268 | 2 |
Payment lines
The latest payments in fiscal year 2026. Checkbook rows
| Date | Department | Fund | Account | Description | Invoice | Amount |
|---|---|---|---|---|---|---|
| May 13, 2026 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | FM08200012805.00 E | $9,714 | |
| January 12, 2026 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | FM08410010266.01 C | $18,887 | |
| January 8, 2026 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | FM08200012805.02 B | $1,167 | |
| January 7, 2026 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | FM08200012805.00a.03B | $1,176 | |
| January 5, 2026 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | FM08200012805.01ab | $287 | |
| January 5, 2026 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | FM08200012805.01aa | $5,450 | |
| January 1, 2026 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | 12805.000 | $2,300 | |
| November 1, 2025 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Project Cost Expenses | CO13191.00A | $9,663 | |
| August 6, 2025 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | FM08740012326.01B | $369 | |
| August 6, 2025 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | FM08740012326.02B | $857 | |
| August 4, 2025 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | FM03510013648.01B | $1,749 | |
| August 4, 2025 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | FM03510013648.00B | $13,118 | |
| August 4, 2025 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | FM03510013648.02B | $691 | |
| August 2, 2025 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | FM08220013230.00D | $78,711 | |
| August 1, 2025 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | 10606.00-E | $24,188 | |
| August 1, 2025 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | FM08220013230.00E | $13,332 | |
| August 1, 2025 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Project Cost Expenses | FM03510013645.00C | $9,604 | |
| August 1, 2025 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | FM08220013230.01B | $790 | |
| July 3, 2025 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | APPLICATION NO 12_9198.01 | $11,168 | |
| July 1, 2025 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | FM08220013230.01A | $15,018 | |
| July 1, 2025 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | 10434.02B | $446 | |
| July 1, 2025 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | APPLICATION NO 11 | $4,940 | |
| July 1, 2025 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | FM08740012235-J | $38,166 | |
| July 1, 2025 | Facilities Management | 30100 Capital Const-Land & Bldg Acq | Buildings-Capital Projects | FM0827009198.01 B | $141 |
Board items naming this vendor
| Date | Item | Amount | Agenda |
|---|---|---|---|
| June 10, 2025 | FACILITIES MANAGEMENT (FM) AND RIVERSIDE COUNTY DISTRICT ATTORNEY’S OFFICE: Southwest Justice Center 3rd Floor Paint and Carpet Replacement Project - Approval of Notice of Completion with Horizons Construction Company International, Inc., Approval to Reprogram Project Savings for use on District Attorney Projects; District 3. [$263,122 - 100% District Attorney General Fund 10000 (Previously approved project budget)] (Clerk to Record Notice of Completion) [$263,122 - 100% District Attorney General Fund 10000 (Previously approved project budget)] | — | Item |
| June 10, 2025 | FACILITIES MANAGEMENT (FM) AND PROBATION DEPARTMENT: Indio Juvenile Hall Air Handler Unit Replacement Project - Approval of Notice of Completion with Horizons Construction Company International, Inc.; District 4. [$24,188 - 100% Probation Department General Fund 10000 (Previously approved project budget)] (Clerk to Record Notice of Completion) [$24,188 - 100% Probation Department General Fund 10000 (Previously approved project budget)] | — | Item |
| May 6, 2025 | FACILITIES MANAGEMENT (FM) AND RIVERSIDE COUNTY INFORMATION TECHNOLOGY: Riverside Countywide Enterprise Wireless Access Point Replacement Project - Approval of Notice of Completion with Horizons Construction Company International, Inc.; All Districts. [$38,166 - 100% ISF Information Technology Fund 45500 (Previously approved budget)] (Clerk to Record Notice of Completion) [$38,166 - 100% ISF Information Technology Fund 45500 (Previously approved budget)] | — | Item |
| March 18, 2025 | FACILITIES MANAGEMENT (FM) AND RIVERSIDE COUNTY INFORMATION TECHNOLOGY AND RIVERSIDE UNIVERSITY HEALTH SYSTEM: Riverside University Health System Facilities Enterprise Wireless Access Point Replacement Project - Approval of Notice of Completion with Horizons Construction Company International, Inc., Districts 1 and 5. [$31,288 - 100% RUHS Enterprise Fund 40050 (Previously approved budget)] (Clerk to Record Notice of Completion) [$31,288 - 100% RUHS Enterprise Fund 40050 (Previously approved budget)] | — | Item |
| February 4, 2025 | FACILITIES MANAGEMENT (FM) AND RIVERSIDE UNIVERSITY HEALTH SYSTEM - PUBLIC HEALTH: Riverside University Health System – Public Health Administration Building Restrooms, Paint and Flooring Renovation Projects - Approval of Notice of Completion with Horizons Construction Company International, Inc. for the Paint and Flooring Portion of the Project; District 1. [$11,929 - RUHS Public Health General Fund 10000 - 55% Federal Funds, 28% State Funds, 17% Local Funds] (Clerk to Record Notice of Completi [$11,929 - RUHS Public Health General Fund 10000 - 55% Federal Funds, 28% State Funds, 17% Local Funds] | $11,929 | Item |
| August 4, 2020 | FACILITIES MANAGEMENT (FM) AND RIVERSIDE COUNTY FIRE DEPARTMENT: Riverside County Fire Department Winchester Station 34 Driveway and Perimeter Fencing Project - Approval of Notice of Completion for Horizons Construction Company, Inc., District 3. [$15,455 – Fire Department General Fund - 51%, Structural Fire Taxes - 49%] (Clerk to Record Notice of Completion) [$15,455 – Fire Department General Fund - 51%, Structural Fire Taxes - 49%] | $15,455 | Item |
| May 19, 2020 | FACILITIES MANAGEMENT (FM) AND RIVERSIDE COUNTY INFORMATION TECHNOLOGY: Riverside County RC3 Data Center Tenant Improvement Project - Approval of Notice of Completion for Horizons Construction Company, Inc., All Districts. [$7,767 - RCIT Operating Budget - 100%] (Clerk to Record Notice of Completion) [$7,767 - RCIT Operating Budget - 100%] | $7,767 | Item |
Sources
Named payees in the County of Riverside checkbook. Every county department is included. City governments are not. A payment has no supervisorial district. Rows with no vendor name are salaries, benefits, and transfers, and they are not listed.
- Check Book · County of Riverside · retrieved 2026-10-10