Hardy & Harper Inc.
Hardy & Harper Inc. is the other party on 1 approved Board action that names Rialto, from September 23, 2025 through September 23, 2025. Recorded spending is ≥ $1.61 million.
How this is counted
Each line is one amount those minutes recorded. A reduction is shown as a lower price, and the document is the file that states it. Read 160 of 183 minutes files. 1 of 4,814 recorded costs are in this total for Rialto.
- Recorded spend in Rialto
- ≥ $1.61 million
- Read 160 of 183 minutes files. 1 of 4,814 recorded costs are in this total for Rialto.
- Line items
- 1
- 0 with a contract number
What the minutes describe
- Construction contract award to Hardy & Harper Inc. for the Blake Street and Other Roads Project - Phase 2.
Line items
Each amount is what that action recorded.
| Date | Amount | Kind | What | Document |
|---|---|---|---|---|
| September 23, 2025 | $1,610,000.00 | Spending | Construction contract award to Hardy & Harper Inc. for the Blake Street and Other Roads Project - Phase 2. Item 102. c. Award Construction Contract to Hardy & Harper Inc. in the amount of $1,610,000 for the Blake Street and Other Roads Project - Phase 2 in the Rialto area. |