Recorded spend in Bloomington
≥ $3.12 million
Read 160 of 183 minutes files. 1 of 4,814 recorded costs are in this total for Bloomington.
Line items
1
0 with a contract number

What the minutes describe

  • Construction contract award for the Bloomington Avenue Pavement and Storm Drain Improvement Project.

Line items

Each amount is what that action recorded.

DateAmountKindWhatDocument
January 9, 2024$3,116,434.00Spending

Construction contract award for the Bloomington Avenue Pavement and Storm Drain Improvement Project.

Item 35. 2. Award a construction contract to Matich Corporation (San Bernardino, CA) in the amount of $3,116,434 for the Bloomington Avenue Pavement and Storm Drain Improvement Project in the Bloomington area.

PDF