Sukut Construction, LLC
Sukut Construction, LLC is the other party on 1 approved Board action that names Colton, from September 13, 2022 through September 13, 2022. Recorded spending is ≥ $35.67 million.
How this is counted
Each line is one amount those minutes recorded. A reduction is shown as a lower price, and the document is the file that states it. Read 160 of 183 minutes files. 1 of 4,814 recorded costs are in this total for Colton.
- Recorded spend in Colton
- ≥ $35.67 million
- Read 160 of 183 minutes files. 1 of 4,814 recorded costs are in this total for Colton.
- Line items
- 1
- 0 with a contract number
What the minutes describe
- Construction contract for the Final Closure Construction Project at the Colton Sanitary Landfill.
Line items
Each amount is what that action recorded.
| Date | Amount | Kind | What | Document |
|---|---|---|---|---|
| September 13, 2022 | $35,667,093.00 | Spending | Construction contract for the Final Closure Construction Project at the Colton Sanitary Landfill. Item 47. 2. Award a construction contract to Sukut Construction, LLC (Santa Ana, California) in the amount of $35,667,093 for the Final Closure Construction Project at the Colton Sanitary Landfill. |