The county paid $72,246 to this name in fiscal year 2015, across 9 payments.

All vendors

How this is counted

The totals are the county checkbook, grouped by department and account. Payment lines are the individual rows behind that total: date, fund, account, description, and invoice. A Board agenda item is listed when its title names this party. The agenda is the board’s record. The checkbook is the payment record. They are not the same document.

By department

DepartmentAccountPaidPayments
Facilities ManagementServices and Support$47,4055
Facilities ManagementCapital Assets$24,8414

Payment lines

The latest payments in fiscal year 2015. Checkbook rows

DateDepartmentFundAccountDescriptionInvoiceAmount
June 1, 2015Facilities Management10000 General FundProject Cost Expenses12795_REV$1,442
May 4, 2015Facilities Management10000 General FundProject Cost Expenses12791$4,589
April 9, 2015District Attorney10000 General FundTraining-Other03/20 - 03/24/15.jj$30
April 9, 2015District Attorney11028 DA Federal Asset ForfeitureTraining-Other03/20 - 03/24/15.jj$34
April 8, 2015Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects12990$3,733
April 8, 2015Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects12914$10,519
April 8, 2015Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects12990$8,961
January 6, 2015Public Health21750 Bio-terrorism PreparednessMiscellaneous Travel ExpenseHays12/9-11/14$24
December 3, 2014Facilities Management10000 General FundProject Cost Expenses12794$2,476
November 19, 2014Rcrmc40050 Riv University Health SystemConference/Registration FeesDB111014$100
November 19, 2014Rcrmc40050 Riv University Health SystemAir TransportationDB111014$148
November 19, 2014Rcrmc40050 Riv University Health SystemMiscellaneous Travel ExpenseDB111014$350
October 21, 2014Facilities Management10000 General FundProject Cost Expenses12792$21,208
August 1, 2014Facilities Management10000 General FundProject Cost Expenses12680$17,690
July 17, 2014District Attorney11028 DA Federal Asset ForfeitureTraining-Other6.13.14 cr$58
July 16, 2014Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects12318$1,628

Board items naming this vendor

DateItemAmountAgenda
January 26, 2021

FACILITIES MANAGEMENT (FM) AND REGIONAL PARK AND OPEN-SPACE DISTRICT: Lake Cahuilla Veterans Regional Park Monument Project - Approval of Notice of Completion for Dalke & Sons Construction, Inc., District 4. [$7,855 – DIF Eastern Riverside County Regional Park Facilities Fund No. 30527 - 100%] (Clerk to Record Notice of Completion)

[$7,855 – DIF Eastern Riverside County Regional Park Facilities Fund No. 30527 - 100%]

$7,855Item
October 8, 2019

ECONOMIC DEVELOPMENT AGENCY (EDA) AND SHERIFF'S DEPARTMENT: Robert Presley Detention Center Control Rooms Flooring Replacement Project - Approval of Notice of Completion for Dalke & Sons Construction, Inc., District 2. [$9,047 - Booking Recovery Fund – 100%] (Clerk to Record Notice of Completion)

[$9,047 - Booking Recovery Fund – 100%]

$9,047Item
October 8, 2019

ECONOMIC DEVELOPMENT AGENCY (EDA): Electric Charging Stations - Multiple Sites - Riverside University Health System Project - Approval of Notice of Completion for Dalke & Sons Construction, Inc., District 5. [$7,618 - EDA Energy Management Budget - General Fund - 100%] (Clerk to Record Notice of Completion)

[$7,618 - EDA Energy Management Budget - General Fund - 100%]

$7,618Item
September 17, 2019

ECONOMIC DEVELOPMENT AGENCY (EDA) AND AGRICULTURAL COMMISSIONER: Riverside County Agricultural Commissioner Office Relocation Project - Approval of Notice of Completion for Dalke & Sons Construction, Inc., District 2. [$16,298 - Departmental Revenue-State and Federal Contracts-88%, Net County Costs–12%] (Clerk to Record Notice of Completion)

[$16,298 - Departmental Revenue-State and Federal Contracts-88%, Net County Costs–12%]

$16,298Item
September 25, 2018

ECONOMIC DEVELOPMENT AGENCY (EDA) AND RIVERSIDE UNIVERSITY HEALTH SYSTEM: Riverside University Health System Inpatient Treatment Facility Fixtures and Hardware Upgrade Project - Approval of Notice of Completion for Dalke & Sons Construction, Inc., District 5. [$34,937 - RUHS Enterprise Fund 40050 - 100%] (Clerk of the Board to Record Notice of Completion)

[$34,937 - RUHS Enterprise Fund 40050 - 100%]

$34,937Item
August 29, 2017

ECONOMIC DEVELOPMENT AGENCY (EDA): Job Order Contract No. 009 - Approval of Construction Contract with Dalke and Sons Construction, Inc., All Districts. [$4.5 Million - Intra-Internal Charges–49%, lnterfund-Reimbursements for Services–50% and Capital Improvement Program Fund–1%]

[$4.5 Million - Intra-Internal Charges–49%, lnterfund-Reimbursements for Services–50% and Capital Improvement Program Fund–1%]

$5Item
June 5, 2012

Approval of Change Order No. 1 with Dalke and Sons Construction, Inc. for Demolition Services – Mission Plaza Improvement Project, 2nd/2nd District.

—Item
June 5, 2012

Approval of Change Order No. 1 with Dalke and Sons Construction, Inc. for Demolition Services – Mission Plaza Improvement Project, 2nd/2nd District.