Falcon Engineering Services Inc

The county paid $3,904,492 to this name in fiscal year 2019, across 32 payments.

All vendors

How this is counted

The totals are the county checkbook, grouped by department and account. Payment lines are the individual rows behind that total: date, fund, account, description, and invoice. A Board agenda item is listed when its title names this party. The agenda is the board’s record. The checkbook is the payment record. They are not the same document.

By department

DepartmentAccountPaidPayments
TransportationServices and Support$3,904,49232

Payment lines

The latest payments in fiscal year 2019. Checkbook rows

DateDepartmentFundAccountDescriptionInvoiceAmount
June 17, 2019Transportation20000 TransportationConsultants2013-60$1,479
June 17, 2019Transportation20000 TransportationConsultants2013-60$12,180
June 17, 2019Transportation20000 TransportationConsultants2013-60$29,035
June 17, 2019Transportation20000 TransportationConsultants2013-60$12,180
June 17, 2019Transportation20000 TransportationConsultants2013-60$1,479
June 17, 2019Transportation20000 TransportationProfessional Services2018-12$279,459
May 22, 2019Transportation20000 TransportationConsultants2018-11$509,435
May 22, 2019Transportation20000 TransportationConsultants2013-59$42,235
April 22, 2019Transportation20000 TransportationConsultants2013-58$1,575
April 22, 2019Transportation20000 TransportationConsultants2013-58$1,260
April 22, 2019Transportation20000 TransportationConsultants2013-58$13,800
April 22, 2019Transportation20000 TransportationConsultants2013-58$59,149
April 22, 2019Transportation20000 TransportationConsultants2013-58$57,587
April 22, 2019Transportation20000 TransportationConsultants2013-58$1,260
April 22, 2019Transportation20000 TransportationConsultants2013-58$1,836
April 17, 2019Transportation20000 TransportationConsultants2018-10$441,210
March 19, 2019Transportation20000 TransportationConsultants2018-09$377,323
February 28, 2019Transportation20000 TransportationConsultants2018-08$455,012
January 17, 2019Transportation20000 TransportationConsultants2018-07$268,429
December 19, 2018Transportation20000 TransportationConsultants2018-06$383,808
December 3, 2018Transportation20000 TransportationConsultants2018-05$277,350
October 30, 2018Transportation20000 TransportationConsultants2018-04REV$310,712
September 25, 2018Transportation20000 TransportationConsultants2013-57R$23,783
September 25, 2018Transportation20000 TransportationConsultants2013-57R$8,400
September 18, 2018Transportation20000 TransportationConsultants2018-03$200,712
August 30, 2018Transportation20000 TransportationConsultants2013-56$9,345
August 10, 2018Transportation20000 TransportationConsultants2018-02$84,058
July 18, 2018Transportation20000 TransportationConsultants2018-01$26,150
July 16, 2018Transportation20000 TransportationConsultants2013-55$2,318
July 16, 2018Transportation20000 TransportationConsultants2013-55$580
July 16, 2018Transportation20000 TransportationConsultants2013-55$4,005
July 16, 2018Transportation20000 TransportationConsultants2013-55$7,350

Board items naming this vendor

DateItemAmountAgenda
January 7, 2025

TRANSPORTATION AND LAND MANAGEMENT AGENCY/TRANSPORTATION: Approval of Amendment No. 2 to the Consulting Services Agreement between the County of Riverside and Falcon Engineering Services, Incorporated, for the Hamner Avenue Bridge Project, District 2. [$1,268,728 Total Amendment Cost, $11,513,573 Total Cost - Federal Funds 88.5%, and State Funds 11.5%]

[$1,268,728 Total Amendment Cost, $11,513,573 Total Cost - Federal Funds 88.5%, and State Funds 11.5%]

$1,268,728Item
August 27, 2024

TRANSPORTATION AND LAND MANAGEMENT AGENCY/TRANSPORTATION: Approval of the On-Call Services Agreement by and between the County of Riverside and Falcon Engineering Services, Incorporated for Construction Management and Inspection Services for FY 24/25 – 28/29. All Districts. [$5,000,000 Total Cost – Capital Funds and Deposit-Based Fees 100%]

[$5,000,000 Total Cost – Capital Funds and Deposit-Based Fees 100%]

$5,000,000Item
August 29, 2023

TRANSPORTATION AND LAND MANAGEMENT AGENCY/TRANSPORTATION: Approval of Amendment No. 1 to the Consulting Services Agreement between the County of Riverside and Falcon Engineering Services, Incorporated for the Hamner Avenue Bridge Project, District 2. [$2,804,526 Total Amendment Cost, $10,244,845 Total Agreement Cost - Federal 88.5%, and State Funds 11.5%]

[$2,804,526 Total Amendment Cost, $10,244,845 Total Agreement Cost - Federal 88.5%, and State Funds 11.5%]

$2,804,526Item
December 8, 2020

TRANSPORTATION AND LAND MANAGEMENT AGENCY/TRANSPORTATION: Approval of the Engineering Services Agreement between the County of Riverside and Falcon Engineering Services, Inc. to Perform Construction Management Services for the Hamner Avenue Bridge Replacement Project. District 2. [$8,000,318 Total Cost - Federal 88.5% and State Funds 11.5%]

[$8,000,318 Total Cost - Federal 88.5% and State Funds 11.5%]

$8,000,318Item
June 18, 2019

TRANSPORTATION AND LAND MANAGEMENT AGENCY/ TRANSPORTATION: Approval of the Engineering Services Agreement by and between the County of Riverside and Falcon Engineering Services Inc. for On-Call Construction Management and Inspection Services for FY 19/20-21/22. All Districts. [Annual $750,000, Total $2,250,000 - Capital Funds and Deposit Based Fees 100%]

[Annual $750,000, Total $2,250,000 - Capital Funds and Deposit Based Fees 100%]

$750,000Item
June 26, 2018

TRANSPORTATION AND LAND MANAGEMENT AGENCY/TRANSPORTATION: Approve Amendment No. 3 to the Agreement for On-Call Construction Engineering Services with Falcon Engineering Services. All Districts; [$350,000 FY 18/19, $3,750,000 Total Costs]; Local Funds 100%

[$350,000 FY 18/19, $3,750,000 Total Costs]

$350,000Item
April 10, 2018

TRANSPORTATION AND LAND MANAGEMENT AGENCY/TRANSPORTATION: Approval of the Engineering Services Agreement by and between the County of Riverside and Falcon Engineering Services, Inc. to Perform Construction Management Services for the Limonite Avenue Interchange Project. 2nd District; [$6,528,381 Total]; Local Funds 100%

[$6,528,381 Total]

$6,528,381Item
March 11, 2014

TRANSPORTATION & LAND MANAGEMENT AGENCY/TRANSPORTATION: Approval of Engineering Services Agreement by and between the County of Riverside and Falcon Engineering Services, Inc. to Perform Construction Management Services for the Magnolia Avenue Grade Separation Project, 2nd/2nd District. [$4,931,900 – 100% Proposition 1B [Trade Corridor Improvement Fund]]

[$4,931,900 – 100% Proposition 1B [Trade Corridor Improvement Fund]

$4,931,900Item

Sources

Named payees in the County of Riverside checkbook. Every county department is included. City governments are not. A payment has no supervisorial district. Rows with no vendor name are salaries, benefits, and transfers, and they are not listed.

  • Check Book · County of Riverside · retrieved 2026-10-10