How this is counted
The totals are the county checkbook, grouped by department and account. Payment lines are the individual rows behind that total: date, fund, account, description, and invoice. A Board agenda item is listed when its title names this party. The agenda is the board’s record. The checkbook is the payment record. They are not the same document.
By department
| Department | Account | Paid | Payments |
|---|---|---|---|
| Transportation | Services and Support | $15,739,527 | 25 |
Payment lines
The latest payments in fiscal year 2013. Checkbook rows
| Date | Department | Fund | Account | Description | Invoice | Amount |
|---|---|---|---|---|---|---|
| June 17, 2013 | Transportation | 20000 Transportation | Contracts | C# 09-04-011 EST 44 | $45,858 | |
| June 11, 2013 | Transportation | 20000 Transportation | Contracts | C# 11-12-005 EST 13 | $642,128 | |
| May 23, 2013 | Transportation | 20000 Transportation | Contracts | C# 09-04-011 EST 43 | $192,887 | |
| May 8, 2013 | Transportation | 20000 Transportation | Contracts | C# 11-12-005 EST 12 | $599,982 | |
| May 1, 2013 | Transportation | 20000 Transportation | Contracts | C# 09-04-011 EST 42 | $279,396 | |
| April 16, 2013 | Transportation | 20000 Transportation | Contracts | C# 11-12-005 EST 11 | $1,910,957 | |
| March 18, 2013 | Transportation | 20000 Transportation | Contracts | C# 09-04-001 EST 41 | $299,335 | |
| March 11, 2013 | Transportation | 20000 Transportation | Contracts | C# 11-12-005 EST 10 | $1,065,433 | |
| February 19, 2013 | Transportation | 20000 Transportation | Contracts | C# 09-04-011 EST 40 | $364,993 | |
| February 7, 2013 | Transportation | 20000 Transportation | Contracts | C# 11-12-005 EST 9 | $317,669 | |
| January 17, 2013 | Transportation | 20000 Transportation | Contracts | C# 09-04-011 EST 39 | $456,073 | |
| January 17, 2013 | Transportation | 20000 Transportation | Contracts | C# 11-12-005 EST 8 | $315,112 | |
| December 13, 2012 | Transportation | 20000 Transportation | Contracts | C# 09-04-011 EST 38 | $1,609,113 | |
| December 4, 2012 | Transportation | 20000 Transportation | Contracts | C# 11-12-005 EST 7 | $273,800 | |
| November 8, 2012 | Transportation | 20000 Transportation | Contracts | C# 09-04-011 EST 37 | $451,212 | |
| November 1, 2012 | Transportation | 20000 Transportation | Contracts | C# 11-12-005 EST 6 | $802,825 | |
| October 4, 2012 | Transportation | 20000 Transportation | Contracts | C# 11-12-005 EST 5 | $927,037 | |
| October 4, 2012 | Transportation | 20000 Transportation | Contracts | C# 09-04-011 EST 36 | $336,313 | |
| September 20, 2012 | Transportation | 20000 Transportation | Contracts | C# 09-04-11 EST 35 | $530,568 | |
| September 11, 2012 | Transportation | 20000 Transportation | Contracts | C# 11-12-005 EST 4 | $828,217 | |
| August 21, 2012 | Transportation | 20000 Transportation | Contracts | C# 11-12-005 EST 3 | $554,540 | |
| August 21, 2012 | Transportation | 20000 Transportation | Contracts | C# 09-04-011 EST 34 | $668,525 | |
| July 30, 2012 | Transportation | 20000 Transportation | Contracts | C# 09-04-011 EST 33 | $435,182 | |
| July 19, 2012 | Transportation | 20000 Transportation | Contracts | C# 11-12-005 EST 2 | $835,870 | |
| July 2, 2012 | Transportation | 20000 Transportation | Contracts | C# 09-04-011 EST 32 | $996,504 |
Board items naming this vendor
| Date | Item | Amount | Agenda |
|---|---|---|---|
| January 13, 2026 | TRANSPORTATION AND LAND MANAGEMENT AGENCY/AVIATION: Approve Change Order No. 3 and approve the Notice of Completion with Griffith Company for the Hemet Ryan Airport Taxiway B, Hangar Taxilanes, and East/West Apron Pavement Rehabilitation Project, District 5. [Total Cost: $8,296 - 100% Airport Budget (Fund 22350)] [Total Cost: $8,296 - 100% Airport Budget (Fund 22350)] | $8,296 | Item |
| October 8, 2024 | TRANSPORTATION AND LAND MANAGEMENT AGENCY/AVIATION: Approve Change Order No. 2 with Griffith Company for the Hemet Ryan Airport Taxiway B, Hangar Taxilanes, and East/West Apron Pavement Rehabilitation Project, District 3. [$280,224 Total Cost - Federal Aviation Administration Airport Improvement Grant Funds 90%, Airport Budget Fund (22350) 10%] [$280,224 Total Cost - Federal Aviation Administration Airport Improvement Grant Funds 90%, Airport Budget Fund (22350) 10%] | $280,224 | Item |
| January 26, 2016 | 3-33 TRANSPORTATION AND LAND MANAGEMENT AGENCY/TRANSPORTATION: Approval of the Agreement with Griffith Company to construct 10 Awning Structures with Concrete Pads at the District Road Maintenance Yards. [$195,000 – Gas Tax 100%] [$195,000 – Gas Tax 100%] | $195,000 | Item |
| April 28, 2015 | 3-35 TRANSPORTATION: Approval of two addenda to the plans and specifications; Acceptance of the low bid and Award of Contract to Griffith Company for the Construction of Grand Avenue Resurfacing and Widening Project; and Approval of the project’s proposed budget, Lakeland Village, 1st District. [$4,523,019 – Redevelopment Excess Bond Proceed 86.9%, Gas Tax 8.4%, Cities Contribution 3.54%, Utility Companies 1.16%] [$4,523,019 – Redevelopment Excess Bond Proceed 86.9%, Gas Tax 8.4%, Cities Contribution 3.54%, Utility Companies 1.16%] | $4,523,019 | Item |