Checkbook
Hazard Construction Company
How this is counted
The totals are the county checkbook, grouped by department and account. Payment lines are the individual rows behind that total: date, fund, account, description, and invoice. A Board agenda item is listed when its title names this party. The agenda is the board’s record. The checkbook is the payment record. They are not the same document.
By department
| Department | Account | Paid | Payments |
|---|---|---|---|
| Transportation | Services and Support | $1,128,478 | 5 |
| Redevelopment Agency | Other Charges | $601,425 | 3 |
Payment lines
The latest payments in fiscal year 2011. Checkbook rows
| Date | Department | Fund | Account | Description | Invoice | Amount |
|---|---|---|---|---|---|---|
| June 22, 2011 | Transportation | 20000 Transportation | Consultants | C# 10-07-007 EST 4 | $357,375 | |
| May 19, 2011 | Transportation | 20000 Transportation | Consultants | C# 10-07-007 EST 3 | $169,975 | |
| April 19, 2011 | Transportation | 20000 Transportation | Consultants | C# 10-07-007 EST 2 | $265,826 | |
| April 19, 2011 | Transportation | 20000 Transportation | Consultants | C# 10-07-007 EST 2 | $1 | |
| March 22, 2011 | Transportation | 20000 Transportation | Contracts | C# 10-07-007 EST 1 | $335,301 | |
| October 25, 2010 | Redevelopment Agency | 32700 Successor Agy Capital Project | Contrib-Project Improv Costs | 15TH | $479,247 | |
| October 25, 2010 | Redevelopment Agency | 32700 Successor Agy Capital Project | Contrib-Project Improv Costs | 20 | $5,425 | |
| October 25, 2010 | Redevelopment Agency | 32700 Successor Agy Capital Project | Contrib-Project Improv Costs | 15TH | $116,753 |
Board items naming this vendor
| Date | Item | Amount | Agenda |
|---|---|---|---|
| August 16, 2011 | Approval of the Findings for the Thermal Town Street Improvement Project; Approval of Addendum 1 to the Contract Documents; Acceptance and Award of Construction Contract to Hazard Construction Company; Approval of the Project Budget; and Approval of the Reimbursement Agreement with the County of Riverside, 4th District. (See item 3.46) | — | Item |
| August 16, 2011 | Approval of the Findings for the Thermal Town Street Improvement Project; Approval of Addendum 1 to the Contract Documents; Acceptance and Award of Construction Contract to Hazard Construction Company; Approval of the Project Budget; and Approval of the Reimbursement Agreement with the County of Riverside, 4th District. (See item 3.46) | — | Item |
Sources
Named payees in the County of Riverside checkbook. Every county department is included. City governments are not. A payment has no supervisorial district. Rows with no vendor name are salaries, benefits, and transfers, and they are not listed.
- Check Book · County of Riverside · retrieved 2026-10-10