Skip to content
Lucid Politics

Checkbook

Kitchell Cem Inc

The county paid $729,606 to this name in fiscal year 2017, across 33 payments.

All vendors

How this is counted

The totals are the county checkbook, grouped by department and account. Payment lines are the individual rows behind that total: date, fund, account, description, and invoice. A Board agenda item is listed when its title names this party. The agenda is the board’s record. The checkbook is the payment record. They are not the same document.

By department

DepartmentAccountPaidPayments
Facilities ManagementCapital Assets$727,52632
Facilities ManagementServices and Support$2,0801

Payment lines

The latest payments in fiscal year 2017. Checkbook rows

DateDepartmentFundAccountDescriptionInvoiceAmount
June 15, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects72516$5,840
June 13, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects72518$65,418
May 1, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects71874$54,940
May 1, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects71013$7,800
May 1, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects71013$820
April 1, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects71406$49,336
March 20, 2017Facilities Management30105 Van Horn Youth Treatmnt/Ed CtrBuildings-Capital Projects70480$26,828
March 13, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings66039$10,813
March 10, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects71003$18,970
March 9, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects71018$160
March 6, 2017Facilities Management30105 Van Horn Youth Treatmnt/Ed CtrBuildings-Capital Projects70932$42,665
February 8, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects70498$6,680
February 8, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects70494$320
February 6, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects70493$19,790
January 23, 2017Facilities Management30105 Van Horn Youth Treatmnt/Ed CtrBuildings-Capital Projects70063$29,392
January 12, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects69983$960
January 4, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects69985$24,260
December 21, 2016Facilities Management30105 Van Horn Youth Treatmnt/Ed CtrBuildings-Capital Projects69516$43,032
December 5, 2016Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects69316$34,435
December 5, 2016Facilities Management10000 General FundProject Cost Expenses69445$2,080
November 17, 2016Facilities Management30105 Van Horn Youth Treatmnt/Ed CtrBuildings-Capital Projects68880$38,039
November 3, 2016Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects68965$30,555
October 18, 2016Facilities Management30100 Capital Const-Land & Bldg AcqBuildings66957$3,000
October 18, 2016Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects68446$22,470
October 18, 2016Facilities Management30105 Van Horn Youth Treatmnt/Ed CtrBuildings-Capital Projects68514$35,073
September 1, 2016Facilities Management30105 Van Horn Youth Treatmnt/Ed CtrBuildings-Capital Projects67950.2$432
September 1, 2016Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects67921$19,260
September 1, 2016Facilities Management30105 Van Horn Youth Treatmnt/Ed CtrBuildings-Capital Projects67950.1$45,552
August 11, 2016Facilities Management30105 Van Horn Youth Treatmnt/Ed CtrBuildings-Capital Projects67352$23,040
August 5, 2016Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects66958$3,510
August 3, 2016Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects67345$13,310
July 25, 2016Facilities Management30105 Van Horn Youth Treatmnt/Ed CtrBuildings-Capital Projects66373.1$1,200
July 19, 2016Facilities Management30105 Van Horn Youth Treatmnt/Ed CtrBuildings-Capital Projects66918$49,627

Board items naming this vendor

DateItemAmountAgenda
June 2, 2026

FACILITIES MANAGEMENT (FM) AND PROBATION DEPARTMENT: Indio Juvenile Hall Master Plan Project - Approval of First Amendment to the Professional Services Agreement with Kitchell/CEM, Inc. for Consulting Services; District 4. [$0]

[$0]

—Item
August 26, 2025

FACILITIES MANAGEMENT (FM) AND PROBATION DEPARTMENT: Indio Juvenile Hall Master Plan Project - Not a Project under the California Environmental Quality Act (CEQA); Approval of In-Principle and Preliminary Project Budget and Approval of Professional Services Agreement with Kitchell/CEM, Inc. for Consulting Services; District 4. [Total Cost $471,526 - 100% Probation Department General Fund 10000]

[Total Cost $471,526 - 100% Probation Department General Fund 10000]

$471,526Item
July 27, 2021

FACILITIES MANAGEMENT (FM) AND RIVERSIDE UNIVERSITY HEALTH SYSTEM: Riverside University Health System Medical Center Exterior Repaint and Repair of Building Envelope Project - Approval of the First Amendment to the Professional Services Agreement for Construction Management Services with Kitchell CEM, Inc. and Approval of Change Order No. 2 and the Notice of Completion with A.J. Fistes Corporation, District 5. [$237,503, 100% RUHS Enterprise Fund 40050 (previously approved budget)] (Clerk to Rec

[$237,503, 100% RUHS Enterprise Fund 40050 (previously approved budget)]

—Item
November 10, 2020

FACILITIES MANAGEMENT AND RIVERSIDE UNIVERSITY HEALTH SYSTEM: Riverside University Health System Medical Center Exterior Repaint and Repair of Building Envelope Project - Approval of Project Budget, Construction Management Services Agreement with Kitchell CEM, Inc. and Approval of Construction Contract with A.J. Fistes Corporation, District 5. [$1,789,807 - RUHS Enterprise Fund 40050 - 100%]

[$1,789,807 - RUHS Enterprise Fund 40050 - 100%]

$1,789,807Item
September 19, 2017

ECONOMIC DEVELOPMENT AGENCY (EDA) AND SHERIFF'S DEPARTMENT: Robert Presley Detention Center Elevator Modernization Project - Approval of Professional Services Agreement with Kitchell CEM, Inc. for Architectural and Engineering Services and Project Reallocation of Funds, District 1. [$128,463 - Capital Improvement Program Fund - 50%, General Fund-Sub Fund 11183 - 50%]

[$128,463 - Capital Improvement Program Fund - 50%, General Fund-Sub Fund 11183 - 50%]

$128,463Item
March 29, 2016

3-42 ECONOMIC DEVELOPMENT AGENCY: Riverside University Health Systems – Emergency Department Expansion and Remodel Project Approval of the Professional Services Agreement for Construction Management Services between the County of Riverside and Kitchell CEM, Inc.; and Approval of the Revised Schematic Design, 5th District. [$1,275,795 – CORAL Bond Proceeds 100%]

[$1,275,795 – CORAL Bond Proceeds 100%]

$1,275,795Item

Sources

Named payees in the County of Riverside checkbook. Every county department is included. City governments are not. A payment has no supervisorial district. Rows with no vendor name are salaries, benefits, and transfers, and they are not listed.

  • Check Book · County of Riverside · retrieved 2026-10-10