Riverside Construction Co Inc

The county paid $22,705,734 to this name in fiscal year 2016, across 32 payments.

All vendors

How this is counted

The totals are the county checkbook, grouped by department and account. Payment lines are the individual rows behind that total: date, fund, account, description, and invoice. A Board agenda item is listed when its title names this party. The agenda is the board’s record. The checkbook is the payment record. They are not the same document.

By department

DepartmentAccountPaidPayments
TransportationServices and Support$22,431,48128
FloodServices and Support$274,2534

Payment lines

The latest payments in fiscal year 2016. Checkbook rows

DateDepartmentFundAccountDescriptionInvoiceAmount
June 20, 2016Transportation20000 TransportationContractsC# 15-01-008 EST#14$1,204,530
May 17, 2016Transportation20000 TransportationContractsC #15-01-008 EST #13$882,166
May 16, 2016Transportation20000 TransportationContractsC #12-03-005 EST #36$11,898
May 16, 2016Transportation20000 TransportationContractsC #13-11-003 EST #25$41,794
April 14, 2016Transportation20000 TransportationContractsC 313-11-003 EST #24$530,558
April 13, 2016Transportation20000 TransportationContractsC #15-01-008 EST #12$1,361,258
March 17, 2016Transportation20000 TransportationContractsC #15-12-009 EST #1$8,954
March 14, 2016Transportation20000 TransportationContractsC #13-11-003 EST #23$830,715
March 14, 2016Transportation20000 TransportationContractsC #15-01-008 EST #11$538,294
March 7, 2016Transportation20000 TransportationContractsC #12-03-005 EST #35$232,340
February 3, 2016Transportation20000 TransportationContractsC #13-11-003 EST #22$226,804
February 3, 2016Transportation20000 TransportationContractsC #15-01-008 EST #10$2,119,034
January 25, 2016Transportation20000 TransportationContractsC #15-01-008 EST #9$851,015
January 12, 2016Transportation20000 TransportationContractsC#13-11-003 EST #21$309,626
December 16, 2015Transportation20000 TransportationContractsC# 15-01-008 EST 8$534,872
December 15, 2015Transportation20000 TransportationContractsC# 13-11-003 EST 20$120,743
November 19, 2015Transportation20000 TransportationContractsC# 15-01-008 EST 7$1,398,025
October 21, 2015Transportation20000 TransportationContractsC# 15-01-008 EST 6$872,539
October 8, 2015Transportation20000 TransportationContractsC# 13-11-003 EST 19$422,267
October 1, 2015Transportation20000 TransportationContractsC# 15-01-008 EST 5$1,303,041
September 16, 2015Flood25150 Zone 5 Const-Maint-MiscContracts10GILHMCHRET0815$5,211
September 16, 2015Flood25150 Zone 5 Const-Maint-MiscContracts10GILHMCHRET0815$8,502
September 16, 2015Flood25150 Zone 5 Const-Maint-MiscContracts10GILHMCHLT10815$161,535
September 16, 2015Flood25150 Zone 5 Const-Maint-MiscContracts10GILHMCHLT10815$99,005
September 15, 2015Transportation20000 TransportationContractsC# 13-11-003 EST 18$448,067
August 18, 2015Transportation20000 TransportationContractsC# 15-01-008 EST 4$1,760,690
August 4, 2015Transportation20000 TransportationContractsC# 13-11-003 EST 17$279,396
August 4, 2015Transportation20000 TransportationContractsC# 12-03-005 EST 34$169,663
July 22, 2015Transportation20000 TransportationContractsC# 13-11-003 EST 16$1,008,582
July 22, 2015Transportation20000 TransportationContractsC# 15-01-008 EST 3$1,837,978
July 15, 2015Transportation20000 TransportationContractsC# 15-01-008 EST 2$3,054,924
July 8, 2015Transportation20000 TransportationContractsC# 12-03-005 EST 33$71,709

Board items naming this vendor

DateItemAmountAgenda
August 27, 2024

TRANSPORTATION AND LAND MANAGEMENT AGENCY/TRANSPORTATION: Notice of Completion and Contract Change Order No. 1 – Between the County of Riverside and Riverside Construction Company, Inc. for the Emergency Bridge Demolition After Storm Damage, North of City of Palm Springs, District 4. [$107,154 Total Cost – Gas Tax 100%]

[$107,154 Total Cost – Gas Tax 100%]

$107,154Item
August 27, 2024

TRANSPORTATION AND LAND MANAGEMENT AGENCY/TRANSPORTATION: Notice of Completion and Contract Change Order No. 1 – Between the County of Riverside and Riverside Construction Company, Inc. for the Emergency Storm Damage Repair Work, Thousand Palms Canyon Road, Ramon Road, Community of Thousand Palms, District 4. [$334,356 Change Order Cost – Gas Tax 100%]

[$334,356 Change Order Cost – Gas Tax 100%]

$334,356Item
May 25, 2021

TRANSPORTATION AND LAND MANAGEMENT AGENCY/TRANSPORTATION: Approve and Execute Contract Change Order No. 7 – Between the County of Riverside and Riverside Construction Co., for the Construction of Avenue 66 at SR-111 and Union Pacific Railroad Grade Separation Project near the Community of Mecca, District 4. [$963,106 Total Cost – Coachella Valley Water District 100%]

[$963,106 Total Cost – Coachella Valley Water District 100%]

$963,106Item
April 10, 2018

TRANSPORTATION AND LAND MANAGEMENT AGENCY/ TRANSPORTATION: Receive and file an Emergency Contract with Riverside Construction Company for Van Buren Boulevard Emergency Pavement Repairs at Interstate 215 and file Notice of Completion of Van Buren Boulevard Emergency Pavement Repairs at Interstate 215. 1st District. [$58,092 Total]; Local Funds 100%

[$58,092 Total]

$58,092Item
February 2, 2016

3-13 Acceptance of the Low Bid and Award of the Contract to Riverside Construction Company, Inc. for the Construction of Briggs Road Low Water Crossing Improvements at Warm Springs Creek, Approval of two addendums to the plans and specifications, and Approval of the Project’s Proposed Budget in the French Valley Area; CEQA Exempt, 3rd District. [$353,820 – Local Funds 100%]

[$353,820 – Local Funds 100%]

$353,820Item
February 10, 2015

TRANSPORTATION AND LAND MANAGEMENT AGENCY/TRANSPORTATION: Jefferson Street at Interstate 10 Project in the City of Indio - Approval of Five Addenda to the Plans and Specifications; Waiver of any minor irregularities, Acceptance of the Low Bid and Award of Contract to Riverside Construction Company, Inc., 4th District. [$42,337,130 – Federal Funds 88%, Local Funds 12%]

[$42,337,130 – Federal Funds 88%, Local Funds 12%]

$42,337,130Item
June 3, 2014

Approval of the Low Bid and Project Award to Riverside Construction Company, Inc. – Gilman Home Channel, Stage 90, 5th/5th District. [$4,113,754 – 100% District Funds]

[$4,113,754 – 100% District Funds]

$4,113,754Item
December 3, 2013

TRANSPORTATION & LAND MANAGEMENT AGENCY/TRANSPORTATION: Sunset Avenue at I-10/Union Pacific Railroad Grade Separation Project in the City of Banning: Approval of three addenda to the plans and specifications; Acceptance of the Low Bid and Award of Contract to Riverside Construction Company, Inc.; and Approval of the Project’s Proposed Budget, 5th/5th District. [$18,237,589 – 15.2% CMAQ / 6.3% STP Discretionary [HR4818] / 6.1% FHWA [SAFETEA-LU] / 31.8% FHWA [Projects of National and Regional Si

[$18,237,589 – 15.2% CMAQ / 6.3% STP Discretionary [HR4818]

$18,237,589Item
November 6, 2012

Approval of the Edison Letter of Authorization and Approval of Change Order Nos. 3 and 4 with Riverside Construction Company, Inc. for the El Cerrito Road and Storm Drain Improvement Project, 2nd/2nd District.

—Item
June 28, 2011

Approval of the Findings for the El Cerrito Road and Storm Drain Improvements; Acceptance of the Low Bid and Award of Construction Contract to Riverside Construction, Inc.; and Approval of the Total Project Budget, 2nd District. (See item 3.47)

—Item
June 28, 2011

Approval of the Findings for the El Cerrito Road and Storm Drain Improvements; Acceptance of the Low Bid and Award of Construction Contract to Riverside Construction, Inc.; and Approval of the Total Project Budget, 2nd District. (See item 3.47)

—Item

Sources

Named payees in the County of Riverside checkbook. Every county department is included. City governments are not. A payment has no supervisorial district. Rows with no vendor name are salaries, benefits, and transfers, and they are not listed.

  • Check Book · County of Riverside · retrieved 2026-10-10