The county paid $270,655 to this name in fiscal year 2018, across 57 payments.

All vendors

How this is counted

The totals are the county checkbook, grouped by department and account. Payment lines are the individual rows behind that total: date, fund, account, description, and invoice. A Board agenda item is listed when its title names this party. The agenda is the board’s record. The checkbook is the payment record. They are not the same document.

By department

DepartmentAccountPaidPayments
Facilities ManagementCapital Assets$176,61849
Facilities ManagementServices and Support$92,6307
Fire ProtectionServices and Support$1,4071

Payment lines

The latest payments in fiscal year 2018. Checkbook rows

DateDepartmentFundAccountDescriptionInvoiceAmount
June 11, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21709$55
May 23, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21807$615
May 18, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21781$45
May 18, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21782$41
May 18, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21780$1,800
May 18, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21779$3,116
May 18, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21778$6,806
May 16, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21795$3,116
May 16, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21794$6,806
May 16, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21796$1,800
May 16, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21746$400
May 9, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21808$415
May 9, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21809$415
May 9, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21806$365
April 24, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21708$55
April 16, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21614$3,650
April 16, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21669$1,245
April 16, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21615$6,150
April 16, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21667$1,845
April 16, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21666$1,095
April 16, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21616$4,150
April 16, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21668$1,245
April 9, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21617$4,150
March 27, 2018Facilities Management10000 General FundProject Cost Expenses21726$10,704
March 12, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21707$61
March 9, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21706$65
March 5, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21582$1,800
March 1, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21580$6,800
February 13, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21665$2,226
January 30, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21584$1,800
January 1, 2018Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21581$1,660
January 1, 2018Facilities Management10000 General FundProject Cost Expenses21539$4,000
December 21, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21587$1,800
December 21, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21583$3,800
December 21, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21578$37
December 21, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21586$3,800
December 21, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21577$1,800
December 21, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21585$1,660
December 21, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21576$1,460
December 21, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects21579$2,460

Board items naming this vendor

DateItemAmountAgenda
December 16, 2025

FACILITIES MANAGEMENT (FM) AND RIVERSIDE UNIVERSITY HEALTH SYSTEM – BEHAVIORAL HEALTH: Riverside University Health System – Behavioral Health Indio Monroe Park Tenant Improvement Project – Approval of the Project Budget and Approval of the First Amendment to the Professional Services Agreement for Architectural Services with STK Architecture, Inc., District 4; [$3,530,131 –100% RUHS Behavioral Health General Fund 10000]

[$3,530,131 –100% RUHS Behavioral Health General Fund 10000]

$3,530,131Item
October 8, 2024

FACILITIES MANAGEMENT (FM) AND PROBATION DEPARTMENT: Indio Juvenile Hall Parking Lot Renovation Project - California Environmental Quality Act (CEQA) Exempt Pursuant to State CEQA Guidelines Section 15301, Class 1 - Existing Facilities Exemption and Section 15061 (b)(3), “Common Sense” Exemption, Approval of In-Principle, Preliminary Design Development Budget, and Approval of Professional Services Agreement with STK Architecture, Inc.; District 4. [Total Cost $235,413 - 100% CIP Fund 30700]

[Total Cost $235,413 - 100% CIP Fund 30700]

$235,413Item
August 16, 2011

Approval of the Architectural and Design Services Agreement with STK Architecture, Inc. for the Mecca Post Office, 4th District.

—Item
August 16, 2011

Approval of the Architectural and Design Services Agreement with STK Architecture, Inc. for the Mecca Post Office, 4th District.

—Item

Sources

Named payees in the County of Riverside checkbook. Every county department is included. City governments are not. A payment has no supervisorial district. Rows with no vendor name are salaries, benefits, and transfers, and they are not listed.

  • Check Book · County of Riverside · retrieved 2026-10-10