Skip to content
Lucid Politics

Checkbook

Vanir Construction Management Inc

The county paid $101,577 to this name in fiscal year 2022, across 5 payments.

All vendors

How this is counted

The totals are the county checkbook, grouped by department and account. Payment lines are the individual rows behind that total: date, fund, account, description, and invoice. A Board agenda item is listed when its title names this party. The agenda is the board’s record. The checkbook is the payment record. They are not the same document.

By department

DepartmentAccountPaidPayments
Facilities ManagementCapital Assets$101,5775

Payment lines

The latest payments in fiscal year 2022. Checkbook rows

DateDepartmentFundAccountDescriptionInvoiceAmount
April 4, 2022Facilities Management30104 Indio Jail Expansion - AB900Buildings-Capital Projects171884$20,789
April 4, 2022Facilities Management30104 Indio Jail Expansion - AB900Buildings-Capital Projects171714$23,516
April 4, 2022Facilities Management30104 Indio Jail Expansion - AB900Buildings-Capital Projects172056$5,879
April 1, 2022Facilities Management30104 Indio Jail Expansion - AB900Buildings-Capital Projects171542$22,064
April 1, 2022Facilities Management30104 Indio Jail Expansion - AB900Buildings-Capital Projects170095$29,329

Board items naming this vendor

DateItemAmountAgenda
April 21, 2020

FACILITIES MANAGEMENT (FM) AND SHERIFF'S DEPARTMENT: John J. Benoit Detention Center – Approval of the Third Amendment to the Professional Services Agreement for Construction Management Services for Vanir Construction Management, Inc., District 4. [$350,000 - Existing JJB Detention Center Bond Proceeds - 100%]

[$350,000 - Existing JJB Detention Center Bond Proceeds - 100%]

$350,000Item
January 29, 2019

ECONOMIC DEVELOPMENT AGENCY (EDA) AND SHERIFF'S DEPARTMENT: John J. Benoit Detention Center – Approval of the Second Amendment to the Professional Services Agreement for Construction Management Services for Vanir Construction Management, Inc., District 4. [$1,800,000 - Existing JJB Detention Center Bond Proceeds - 100%]

[$1,800,000 - Existing JJB Detention Center Bond Proceeds - 100%]

$1,800,000Item
June 19, 2018

ECONOMIC DEVELOPMENT AGENCY (EDA): Southwest Justice Center Courts Relocation – Ratify and Approve First Amendment to the Professional Services Agreement with Vanir Construction Management, Inc. for Construction Management Services, and Approval of the Notices of Completion for the Awarded Multi-Prime Contractors, District 3. [$674,703 – Existing JJB Detention Center Bond Proceeds - 100%] (Clerk to Record Notices of Completion)

[$674,703 – Existing JJB Detention Center Bond Proceeds - 100%]

$674,703Item
February 27, 2018

ECONOMIC DEVELOPMENT AGENCY (EDA) AND SHERIFF'S DEPARTMENT: John J. Benoit Detention Center – Approval of Revised Project Budget, Amendment No. 1 to the Professional Services Agreement for Construction Management Services for Vanir Construction Management, Inc., District 4. [$10,248,331–Existing JJB Detention Center Bond Proceeds 100%]

[$10,248,331–Existing JJB Detention Center Bond Proceeds 100%]

$10,248,331Item
September 1, 2015

3-11 Southwest Justice Center Courts Relocation – Approval of Construction Management Services Agreement between the County of Riverside and Vanir Construction Management, Inc., 3rd District. [$1,080,219 – Bond Proceeds 100%]

[$1,080,219 – Bond Proceeds 100%]

$1,080,219Item

Sources

Named payees in the County of Riverside checkbook. Every county department is included. City governments are not. A payment has no supervisorial district. Rows with no vendor name are salaries, benefits, and transfers, and they are not listed.

  • Check Book · County of Riverside · retrieved 2026-10-10