The county paid $240,414 to this name in fiscal year 2011, across 2 payments.

All vendors

How this is counted

The totals are the county checkbook, grouped by department and account. Payment lines are the individual rows behind that total: date, fund, account, description, and invoice. A Board agenda item is listed when its title names this party. The agenda is the board’s record. The checkbook is the payment record. They are not the same document.

By department

DepartmentAccountPaidPayments
Facilities ManagementCapital Assets$240,4142

Payment lines

The latest payments in fiscal year 2011. Checkbook rows

DateDepartmentFundAccountDescriptionInvoiceAmount
April 14, 2011Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital ProjectsT03138$234,910
February 1, 2011Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital ProjectsT26601$5,504

Board items naming this vendor

DateItemAmountAgenda
April 21, 2020

FACILITIES MANAGEMENT (FM) AND SHERIFF'S DEPARTMENT: John J. Benoit Detention Center – Approval of the Third Amendment to the Professional Services Agreement for Construction Management Services for Vanir Construction Management, Inc., District 4. [$350,000 - Existing JJB Detention Center Bond Proceeds - 100%]

[$350,000 - Existing JJB Detention Center Bond Proceeds - 100%]

$350,000Item
January 29, 2019

ECONOMIC DEVELOPMENT AGENCY (EDA) AND SHERIFF'S DEPARTMENT: John J. Benoit Detention Center – Approval of the Second Amendment to the Professional Services Agreement for Construction Management Services for Vanir Construction Management, Inc., District 4. [$1,800,000 - Existing JJB Detention Center Bond Proceeds - 100%]

[$1,800,000 - Existing JJB Detention Center Bond Proceeds - 100%]

$1,800,000Item
June 19, 2018

ECONOMIC DEVELOPMENT AGENCY (EDA): Southwest Justice Center Courts Relocation – Ratify and Approve First Amendment to the Professional Services Agreement with Vanir Construction Management, Inc. for Construction Management Services, and Approval of the Notices of Completion for the Awarded Multi-Prime Contractors, District 3. [$674,703 – Existing JJB Detention Center Bond Proceeds - 100%] (Clerk to Record Notices of Completion)

[$674,703 – Existing JJB Detention Center Bond Proceeds - 100%]

$674,703Item
February 27, 2018

ECONOMIC DEVELOPMENT AGENCY (EDA) AND SHERIFF'S DEPARTMENT: John J. Benoit Detention Center – Approval of Revised Project Budget, Amendment No. 1 to the Professional Services Agreement for Construction Management Services for Vanir Construction Management, Inc., District 4. [$10,248,331–Existing JJB Detention Center Bond Proceeds 100%]

[$10,248,331–Existing JJB Detention Center Bond Proceeds 100%]

$10,248,331Item
September 1, 2015

3-11 Southwest Justice Center Courts Relocation – Approval of Construction Management Services Agreement between the County of Riverside and Vanir Construction Management, Inc., 3rd District. [$1,080,219 – Bond Proceeds 100%]

[$1,080,219 – Bond Proceeds 100%]

$1,080,219Item