The county paid $1,847,665 to this name in fiscal year 2018, across 14 payments.

All vendors

How this is counted

The totals are the county checkbook, grouped by department and account. Payment lines are the individual rows behind that total: date, fund, account, description, and invoice. A Board agenda item is listed when its title names this party. The agenda is the board’s record. The checkbook is the payment record. They are not the same document.

By department

DepartmentAccountPaidPayments
Facilities ManagementCapital Assets$1,847,66514

Payment lines

The latest payments in fiscal year 2018. Checkbook rows

DateDepartmentFundAccountDescriptionInvoiceAmount
May 29, 2018Facilities Management30104 Indio Jail Expansion - AB900Buildings-Capital Projects163032$134,893
May 7, 2018Facilities Management30104 Indio Jail Expansion - AB900Buildings-Capital Projects162932$153,170
March 20, 2018Facilities Management30104 Indio Jail Expansion - AB900Buildings-Capital Projects162765$115,080
March 7, 2018Facilities Management30104 Indio Jail Expansion - AB900Buildings-Capital Projects162326$131,969
March 7, 2018Facilities Management30104 Indio Jail Expansion - AB900Buildings-Capital Projects161967$149,291
March 7, 2018Facilities Management30104 Indio Jail Expansion - AB900Buildings-Capital Projects162608$140,078
March 7, 2018Facilities Management30104 Indio Jail Expansion - AB900Buildings-Capital Projects162141$174,921
March 7, 2018Facilities Management30104 Indio Jail Expansion - AB900Buildings-Capital Projects162431$166,879
October 5, 2017Facilities Management30104 Indio Jail Expansion - AB900Buildings-Capital Projects161781$169,124
August 28, 2017Facilities Management30104 Indio Jail Expansion - AB900Buildings-Capital Projects161580$146,305
August 2, 2017Facilities Management30104 Indio Jail Expansion - AB900Buildings-Capital Projects161494$159,090
July 24, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects161381$5,148
July 20, 2017Facilities Management30100 Capital Const-Land & Bldg AcqBuildings-Capital Projects161028$67,235
July 3, 2017Facilities Management30104 Indio Jail Expansion - AB900Buildings-Capital Projects161298$134,482

Board items naming this vendor

DateItemAmountAgenda
April 21, 2020

FACILITIES MANAGEMENT (FM) AND SHERIFF'S DEPARTMENT: John J. Benoit Detention Center – Approval of the Third Amendment to the Professional Services Agreement for Construction Management Services for Vanir Construction Management, Inc., District 4. [$350,000 - Existing JJB Detention Center Bond Proceeds - 100%]

[$350,000 - Existing JJB Detention Center Bond Proceeds - 100%]

$350,000Item
January 29, 2019

ECONOMIC DEVELOPMENT AGENCY (EDA) AND SHERIFF'S DEPARTMENT: John J. Benoit Detention Center – Approval of the Second Amendment to the Professional Services Agreement for Construction Management Services for Vanir Construction Management, Inc., District 4. [$1,800,000 - Existing JJB Detention Center Bond Proceeds - 100%]

[$1,800,000 - Existing JJB Detention Center Bond Proceeds - 100%]

$1,800,000Item
June 19, 2018

ECONOMIC DEVELOPMENT AGENCY (EDA): Southwest Justice Center Courts Relocation – Ratify and Approve First Amendment to the Professional Services Agreement with Vanir Construction Management, Inc. for Construction Management Services, and Approval of the Notices of Completion for the Awarded Multi-Prime Contractors, District 3. [$674,703 – Existing JJB Detention Center Bond Proceeds - 100%] (Clerk to Record Notices of Completion)

[$674,703 – Existing JJB Detention Center Bond Proceeds - 100%]

$674,703Item
February 27, 2018

ECONOMIC DEVELOPMENT AGENCY (EDA) AND SHERIFF'S DEPARTMENT: John J. Benoit Detention Center – Approval of Revised Project Budget, Amendment No. 1 to the Professional Services Agreement for Construction Management Services for Vanir Construction Management, Inc., District 4. [$10,248,331–Existing JJB Detention Center Bond Proceeds 100%]

[$10,248,331–Existing JJB Detention Center Bond Proceeds 100%]

$10,248,331Item
September 1, 2015

3-11 Southwest Justice Center Courts Relocation – Approval of Construction Management Services Agreement between the County of Riverside and Vanir Construction Management, Inc., 3rd District. [$1,080,219 – Bond Proceeds 100%]

[$1,080,219 – Bond Proceeds 100%]

$1,080,219Item

Sources

Named payees in the County of Riverside checkbook. Every county department is included. City governments are not. A payment has no supervisorial district. Rows with no vendor name are salaries, benefits, and transfers, and they are not listed.

  • Check Book · County of Riverside · retrieved 2026-10-10